Percentage of completion under ASC 606 for contractors
November 18, 2026 · 10 min read

Quick answer
Under ASC 606, most construction contracts are recognized as revenue over time, as the work gets done, and the usual way to measure how far along a job is the cost-to-cost method: costs incurred to date divided by total estimated costs. That percentage times the contract price is the revenue you've earned. Compare it with what you've billed and you get overbillings or underbillings, which is exactly what your bank and surety will look at.
Your bonding agent wants a WIP schedule by the 20th. Your bank wants year-end financial statements "prepared on GAAP." And your books record revenue every time an invoice goes out, so your income statement tracks billing, not the work.
Percentage of completion isn't a separate rule anymore. Since ASC 606 replaced the old construction guidance, it's simply how most contractors apply the revenue standard. (For the general model, see the ASC 606 five steps.) This post covers the construction side: a worked example, uninstalled materials, change orders, losing jobs, a four-job WIP schedule and a short note on taxes.
When does a contractor recognize revenue over time?
ASC 606 says revenue is recognized over time if any one of three conditions is met:
- The customer receives and uses the benefit as you perform (service and maintenance work).
- Your work creates or improves an asset the customer controls as it's built, like building on the owner's land.
- Your work creates an asset with no alternative use to you, and you have an enforceable right to payment for work done to date.
Most construction contracts meet the second or third condition easily. If none is met, revenue waits until control transfers, usually at completion. Check your termination clauses: no right to be paid for work done if the customer walks away can change the answer.
How does the cost-to-cost method work?
ASC 606 lets you measure progress with an input method (effort spent: costs, labor hours) or an output method (results delivered: milestones, units installed). Most contractors use an input method, and the most common one is cost-to-cost:
- Percent complete = costs incurred to date ÷ total estimated costs
- Revenue earned to date = percent complete × contract price
- Revenue this period = revenue earned to date − revenue recognized in earlier periods
The formula is easy. The hard part is the denominator: total estimated cost is your project managers' judgment, and it should be updated every month. Costs that don't reflect progress, like rework or wasted materials, are left out of the measure.
A worked example: one job, four months
Say you're an electrical contractor with a $1,200,000 contract to wire a new medical office building. You estimate the job will cost $1,000,000, for an expected gross profit of $200,000. Work starts in June. Here's where things stand at the end of September:
| Line | Amount |
|---|---|
| Contract price | $1,200,000 |
| Estimated total cost | $1,000,000 |
| Costs incurred to date | $450,000 |
| Percent complete ($450,000 ÷ $1,000,000) | 45% |
| Revenue earned to date (45% × $1,200,000) | $540,000 |
| Gross profit to date ($540,000 − $450,000) | $90,000 |
| Billed to date | $600,000 |
| Overbilled ($600,000 − $540,000) | $60,000 |
You've invoiced $60,000 more than you've earned. That's a contract liability ("billings in excess of costs and estimated earnings" on most WIP schedules), on the balance sheet, not in revenue.
Here's how the gap built up, with costs to date of $90,000, $200,000, $320,000 and $450,000:
Revenue earned vs billed to date, electrical job
Hypothetical $1.2M contract, cumulative at each month end
- Revenue earned to date
- Billed to date
Hypothetical example. Percent complete is 9%, 20%, 32% and 45%. Overbilled by $12,000 in June, even in July, $36,000 in August and $60,000 in September.
Show the numbers
| Revenue earned to date | Billed to date | |
|---|---|---|
| Jun | $108,000 | $120,000 |
| Jul | $240,000 | $240,000 |
| Aug | $384,000 | $420,000 |
| Sep | $540,000 | $600,000 |
Booked as billed, September would show $600,000 of revenue and $150,000 of gross profit on this job. The real figures are $540,000 and $90,000.
What happens with uninstalled materials?
Say $100,000 of the $450,000 in September is switchgear delivered to site but not yet installed. Under plain cost-to-cost, buying expensive equipment would make the job look further along than it is, and you'd book margin on equipment that's sitting in crates.
When the materials aren't distinct from the rest of the job, the customer gets control of them before they're installed, their cost is significant relative to the whole job, and you didn't design or make them, the standard lets you adjust: recognize revenue equal to the cost of those materials (zero margin) and measure progress on the rest of the work.
| Plain cost-to-cost | Adjusted for uninstalled switchgear | |
|---|---|---|
| Costs counted toward progress | $450,000 of $1,000,000 | $350,000 of $900,000 |
| Percent complete | 45% | about 38.9% |
| Revenue from the work | $540,000 | about $427,800 ($350,000 ÷ $900,000 × $1,100,000) |
| Revenue from the switchgear, at cost | n/a | $100,000 |
| Revenue earned to date | $540,000 | about $527,800 |
The difference, roughly $12,200, is margin that would otherwise have been booked on equipment nobody has installed yet. It comes back once the switchgear goes in.
How do change orders and claims fit in?
Under ASC 606, a change order is a contract modification: an approved change in scope, price or both. Most aren't distinct from the original work (more wiring in the same building), so they're folded into the existing contract: update the price and estimated total cost, recompute percent complete, and take the cumulative effect in the current period.
The tricky ones are unpriced change orders (the scope is agreed, the price isn't) and claims (amounts you're seeking that the customer disputes). Both are variable consideration. You estimate what you expect to collect and include it in the price only to the extent it's probable that a significant reversal of revenue won't happen later. That takes evidence: an approved scope, a history of converting similar items to signed change orders, and a sensible estimate. A disputed claim rarely clears that bar. The costs of the extra work, meanwhile, count as you spend them, so margin dips until the price is settled.
What if a job is going to lose money?
ASC 606 didn't bring its own rule for losing contracts, so the old construction guidance (ASC 605-35) still applies: once you can see that a job's total costs will exceed its price, the entire expected loss is recorded right away, not spread over the remaining months.
Back to our electrical job. In October, before much more is spent, your project manager re-estimates total cost at $1,250,000 because of a redesign the owner won't pay for. The job will now lose $50,000. With costs still at $450,000, percent complete drops to 36%, so revenue earned to date falls to $432,000. Gross loss to date is $18,000, and the remaining $32,000 of the expected loss is recorded now as a loss provision.
What the October re-estimate does to the job's result
Same hypothetical electrical job, cumulative gross profit
- Raises profit
- Lowers profit
- Total
Hypothetical example. 90,000 − 108,000 − 32,000 = −50,000, the full expected loss ($1,200,000 price − $1,250,000 cost).
Show the numbers
| Gross profit through September | $90,000 |
| Revenue reversed (45% to 36%) | −$108,000 |
| Rest of the expected loss, recorded now | −$32,000 |
| Job result after re-estimate | −$50,000 |
October takes a $140,000 hit on one job. Painful, but you see the loss while you can still act, not at closeout. The overbilling also jumps to $168,000 ($600,000 billed against $432,000 earned). A growing overbilling on a shrinking margin is one of the clearest warning signs there is.
What does a WIP schedule look like across several jobs?
The WIP schedule runs the same math for every open job, every month. Here's September with three more jobs (the electrical job is Job 101, before the re-estimate):
| Job | Contract price | Est. total cost | Costs to date | % complete | Earned to date | Billed to date | Overbilled | Underbilled |
|---|---|---|---|---|---|---|---|---|
| 101 | $1,200,000 | $1,000,000 | $450,000 | 45% | $540,000 | $600,000 | $60,000 | |
| 102 | $800,000 | $680,000 | $510,000 | 75% | $600,000 | $560,000 | $40,000 | |
| 103 | $450,000 | $400,000 | $100,000 | 25% | $112,500 | $150,000 | $37,500 | |
| 104 | $300,000 | $240,000 | $228,000 | 95% | $285,000 | $285,000 | ||
| Total | $2,750,000 | $2,320,000 | $1,288,000 | $1,537,500 | $1,595,000 | $97,500 | $40,000 |
Overbillings of $97,500 go on the balance sheet as a liability and underbillings of $40,000 as an asset (overbilling and underbilling explained). Net, the company has billed $57,500 ahead of its work.
Why do banks and sureties read this so closely? Because it shows what the income statement can't. Job 102 is underbilled by $40,000: work done but not invoiced, which can mean slow billing or costs that won't be recovered. Job 103 is heavily front-billed at 25% complete. And backlog (price minus earned, $1,212,500 here) is the work still to finance. A surety sizing your bonding capacity reads it job by job, and profit that fades from one schedule to the next is a red flag.
For the bookkeeping that feeds the schedule, our post on construction bookkeeping mistakes covers job costing, retainage and the subcontractor paperwork.
How is percentage of completion different for taxes?
Your books follow ASC 606. Your tax return follows Internal Revenue Code Section 460, and the two often don't match.
GAAP
Financial statements (ASC 606)
- Over time when one of the three conditions is met
- Progress usually measured by cost-to-cost
- Full expected loss recorded when evident
- What your bank and surety read
Tax
Tax return (Section 460)
- Long-term contracts generally use percentage of completion
- Small contractor exception for qualifying contracts
- Home construction contracts excepted, widened by the 2025 tax law to residential construction contracts
- Look-back interest (Form 8697) when estimates prove wrong
The small contractor exception covers a construction contract you expect to finish within 2 years of starting it, if you meet the gross receipts test for the year you sign it. For tax years beginning in 2026 that test is average annual gross receipts of $32 million or less over the three prior tax years (it was $31 million for 2025, and it's indexed for inflation). Gross receipts of related businesses are added together. Contracts that qualify can use another method, such as completed contract, which can defer tax.
Choosing or changing a tax method is your CPA's call. Your job is clean job costing to support it.
Common mistakes
Booking revenue as you bill. It's the default in most accounting software and it's wrong for GAAP. Revenue follows the work, and the difference lives on the balance sheet.
Estimates nobody updates. If total estimated cost hasn't changed since the bid, percent complete is fiction.
Counting uninstalled materials and rework as progress. Both pull margin forward.
Pricing in unpriced change orders and claims too early. No approved scope or supportable amount, no revenue.
Spreading a loss. Record the whole expected loss when it shows up.
Spending overbillings. That cash is owed back as work. Spend it on overhead and you'll finish the job without it.
When should you get help?
A couple of short jobs a year and no lender asking for GAAP statements? A spreadsheet WIP schedule and a careful year-end entry may be enough.
Get help when you run several jobs at once, when a surety or lender wants a WIP schedule every quarter, when change orders and claims are a real share of revenue, or when a loss surprised you at closeout. Fintrix Consulting builds that reporting and runs the month-end close for contractors; see how we work with real estate and construction businesses or our accounting services.
Frequently asked questions
Is percentage of completion still allowed under ASC 606?
Yes, in substance. ASC 606 replaced the old construction guidance, but for contracts recognized over time, an input method like cost-to-cost produces percentage of completion accounting. The old completed contract method is no longer a GAAP option; revenue waits until the end only when control really transfers at completion.
What's the difference between overbilling and underbilling?
Overbilling means you've billed more than you've earned based on percent complete; it's a liability. Underbilling means you've earned more than you've billed; it's an asset. Both come from comparing billed to date with revenue earned to date, job by job.
Do small contractors have to follow ASC 606?
If you issue GAAP financial statements, yes, whatever your size. Tax rules are separate, and smaller contractors often qualify for an exception.
Where does retainage go on the WIP schedule?
Retainage is part of what you've billed, so it's included in billed to date. It's tracked separately on the balance sheet because it isn't collectible until the conditions in the contract are met. See retainage in our glossary.
The bottom line
Percentage of completion under ASC 606 comes down to a few habits: measure progress honestly with cost-to-cost, keep uninstalled materials, unpriced change orders and claims out until they belong, and record losses the moment you see them. Put it on a monthly WIP schedule and you'll know which jobs make money while you can still act. Keep the tax side separate and let your CPA pick the Section 460 method.
Sources
- The ASC 606 transition for construction contractors: Recognizing revenue (Baker Tilly)
- Revenue recognition for contractors (Baker Tilly)
- Instructions for Form 8697 (Rev. December 2025) (IRS)
- Revenue Procedure 2025-32, 2026 inflation adjustments, section 4.30 (IRS)
- Revenue Procedure 2026-32, accounting method changes incl. residential construction contracts (IRS)
This article is general information, not advice for your situation. Rules change and details matter, so talk to us or your CPA before acting on it.
More articles
- Construction bookkeeping mistakes: job costing, retainage and WIP
November 18, 2026
- Bookkeeping for medical and dental practices: what's different
November 18, 2026
- Trust accounting basics for law firms
November 18, 2026
Have a question about this article?
Ask us. A real person will reply by email within one business day. Your question isn’t published.
Ready for books you can trust?
Book a free 30-minute consultation. We'll review where your finances stand today and show you exactly how we'd help.